Progress update 6-20

Building 1 electrical roughs have progressed through unit 2 (2505) and as you can see in the photos below the exterior siding is nearing completion. We are currently testing exterior building colors and think [...]

By | June 21st, 2017|Categories: Uncategorized|Comments Off on Progress update 6-20

Progress Update 5/16/17

Building 1 MEP installation has seen some good progress over the last couple weeks with the HVAC roughs complete through all 6 units. The plumbers are now working in Unit 2801 and electricians will [...]

By | May 16th, 2017|Categories: Uncategorized|Comments Off on Progress Update 5/16/17

Progress Update 4/25

Building 1 has finished up the roof and decking membrane and exterior Tyvek wrap continues. HVAC roughs are now underway in Unit 2801.   Building 2 framing continues with 3rd level floor joists now [...]

By | April 25th, 2017|Categories: Uncategorized|Comments Off on Progress Update 4/25

Decatur 12 Progress Update 4/19

We are kicking off our Decatur 12 project halfway through the framing process. Building 1 is near 100% framed with only a few details remaining on the balconies. The roof membrane and windows are [...]

By | April 20th, 2017|Categories: Uncategorized|Comments Off on Decatur 12 Progress Update 4/19